Apprenticeship Accountability Framework
The Apprenticeship Accountability Framework report shows risk areas for providers along with a risk rating, based on the Apprenticeship Accountability Framework documentation and guidance.
Clicking on a figure will show a drilldown of the learners and aims which comprise that figure. The columns included in the drilldown are specific to that particular indicator, to show data relevant to the derivation of the figure.
Parameters
-
Year - Shows data for the selected year.
-
Centre - Filters by the selected centres.
-
Contractor - Filters by the selected contractors.
-
Merge planned break / restart POTs into single record - See below for details.
-
Ready to run - Set this to Yes once all other parameters have been set as required.
Criteria
The following should be noted while reading the criteria:
-
References to @year mean the year selected in the parameters.
References to contractyear mean the contract year selected in the parameters; e.g. 2021/22 = 2122.
-
References to totalapps mean the total apprentices counted in the year, defined as POTs where:
-
programme type is 2, 3, 10, 20, 21, 22, 23 or 25
-
AND the programme aim is active in the selected year, based on programme aim dates (e.g. for 2021/22, programme start date is <= 31/07/2022 and either programme actual end date is not entered or is >= 01/08/2021)
-
-
If neither the At Risk or Needs Improvement criteria is met, the status is considered On Track. If the criteria is met for both At Risk and Needs Improvement, the status is At Risk.
Indicator | Figure | Derivation | At Risk | Needs Improvement |
---|---|---|---|---|
Achievement rates (QAR) | Achievers | TRAINEEPPR.FRAME = @year | Achievement rate < 50% | Achievement rate >= 50% and < 60% |
Overall cohort | TRAINEEPPR.OVERALLCOHORT = @year | |||
Achievement rate | Percentage of achievers / overall cohort | |||
Retention rates (QAR) | Retention | TRAINEEPPR.RETENTION = @year | Retention rate < 52% | Retention rate >= 52% and < 62% |
Overall cohort | TRAINEEPPR.OVERALLCOHORT = @year | |||
Retention rate | Percentage of retention / overall cohort | |||
Withdrawals | Withdrawals | totalapps where programme aim completion status [TRAINEEPOT2.ILR11_PROG_COMPLETIONSTAUS] = 3 | Withdrawal rate > 35% | (Withdrawal rate <= 35% and > 15%) OR withdrawals > 250" |
Total apprentices | totalapps | |||
Withdrawal rate | Percentage of withdrawals / totalapps | |||
Off the job training | Apprentices below planned OTJ threshold |
First, the minimum weekly OTJ hours is derived based on the employment status Employment Intensity Indicator (EII) as:
(EII values 1 to 4 are ignored as they are no longer used.)
Next, the planned programme length in weeks is derived as the number of weeks between the programme start date and planned end date. The method used for measuring weeks is the SQL Server datediff function; i.e. datediff(week,[prog start date],[prog planned end date]).
The annual leave adjustment is set at 0.892, which is rounded from the ESFA's multiplier of (1 - (5.6 / 52)).
The total minimum required OTJ hours is calculated as: minimum weekly hours x planned weeks x 0.892 x 0.2 e.g. With an EII of 8 and a planned programme length of 52 weeks, the total min required OTJ hours would be: 30 x 52 x 0.892 x 0.2 = 278.304 hours.
The ILR planned hours (TRAINEEPOT.ILR_1920_PLANNEDHOURS) and actual hours (TRAINEEPOT.ILR_2021_ACTHOURS) are then each compared against the min OTJ hours. If the planned hours are less than the min OTJ hours, the learner is considered below the minimum required planned hours. |
totalapps below planned OTJ threshold +totalapps below actual OTJ threshold > 20 OR totalapps present with 0 planned hours or 0 actual hours |
totalapps below planned OTJ threshold > 15 OR totalapps below actual OTJ threshold > 0 |
Apprentices below actual OTJ threshold | Derive figures as above. If the actual hours are less than the min OTJ hours AND the programme completion status is 2 (completed), the learner is considered below the minimum required actual hours (i.e. the actual hours are only relevant if the learner has completed). | |||
Apprentices with 0 planned hours OR 0 actual hours on completion | totalapps where planned hours [TP.ILR_1920_PHOURS] = 0 OR actual hours [TP.ILR_2021_ACTHOURS] = 0 | |||
Learners past planned end date | Total apprentices | totalapps | Apprentices past PED by 365+ days percentage > 15% |
Apprentices past PED by 180 to 364 days percentage > 15% OR Apprentices past PED by 180 to 364 days records > 250 |
Apprentices past PED by 365+ days |
Derive daysoverdue as: days between programme planned end date and (if programme actual end date is entered then programme actual end date, else current date) Then count totalapps where daysoverdue >= 365 |
|||
Apprentices past PED by 180 to 364 days | ||||
Breaks in learning | Total apprentices | totalapps | Apprentices on a break in learning for 365+ days percentage > 15% | Apprentices on a break in learning for 180 to 364 days percentage > 15% OR Apprentices on a break in learning for 180 to 364 days records > 250 |
Apprentices on a break in learning for 365+ days |
First, derive norestart (i.e. learners on a break with no restart record) as totalapps where:
If all the above is true, norestart = Y Next count daysonbreak as the days between the programme aim actual end date on the break record and the current date The final figure is the totalapps where norestart = Y and daysonbreak >= 365 |
|||
Apprentices on a break in learning for 180 to 364 days |
Derive norestart and daysonbreak as above The final figure is the totalapps where norestart = Y and daysonbreak >= 180 and < 365 |
|||
End point assessment organisation data | No EPA within 3 months of PED |
First, derive liveapps as totalapps where no programme aim actual end date is entered (i.e. live records) and where there is no prog aim EPA organisation ID entered [TRAINEEPOT.ILR_1718_PROG_EPAORGID] Then count liveapps where the programme planned end date <= current date + 3 months |
No EPA within 3 months of PED > 0 | No EPA within 3 to 6 months of PED > 0 |
No EPA within 3 to 6 months of PED | Derive liveapps as above, then count liveapps where the programme planned end date > current date + 3 months and <= current date + 6 months |
Merge multiple POTs into single programme
The Apprenticeship Accountability Framework report will by default merge multiple POTs from planned breaks / restarts into a single programme in the results. This can be toggled with the Merge planned break / restart POTs into a single record parameter.
This feature is implemented in the Withdrawals, Off the job training, Learners past planned end date and End point assessment organisation data measures, so that programmes that have restarted are not counted more than once.
The feature is not implemented in the Achievement rates, Retention rates and Breaks in learning measures, as these have their own specific rules for how breaks / restarts are measured and presented.
POTs are merged into a single programme by first identifying POTs where the programme aim completion status is 6 or the restart indicator is 1. These POTs are then matched as part of the same programme on ULN, learner reference number, UKPRN and framework or standard code. The following data is then used in the measures:
Field | Data used |
---|---|
POT | Latest POT in the programme (based on start date) |
Start date | Earliest programme start date of all POTs in the programme |
Planned end date | Latest programme planned end date of all POTs in the programme |
Actual end date | Latest programme actual end date of all POTs in the programme |
Completion status | Latest programme completion status of all POTs in the programme |